Take-off against stock 8 SKUs · quantities off the solid
| Material |
Required |
In stock |
To order |
Source |
Lead |
Status |
| Fibreglass shell, kidney 10.4TP-SHL-K1040 |
1 |
0 |
1 |
Own factory, mould M-3 |
2 wk |
Mould slotted |
| Spotted gum decking, 140 × 19TP-DEK-SPG |
452 lm |
280 lm |
172 lm |
Timberline, Wetherill Park |
5 d |
PO-2211 |
| Bullnose coping, 500 mm unitsTP-COP-BN |
61 |
64 |
— |
Ex yard |
— |
Reserved |
| Glass panel 12 mm, 1200 × 1200TP-BAR-GL12 |
33 |
12 |
21 |
Cut to order, Glasscorp |
15 d |
PO-2212 |
| Gate, hinges & latch setTP-BAR-GATE |
1 |
3 |
— |
Ex yard |
— |
Reserved |
| Pump, filter & chlorinator setTP-PLT-SET |
1 |
0 |
1 |
Waterco, distribution |
4 d |
PO-2213 |
| Hydraulic pipe & fittings, 50 mmTP-HYD-50 |
46 m |
120 m |
— |
Ex yard |
— |
Reserved |
| Bedding sand & aggregateTP-CIV-BED |
18 t |
30 t |
— |
Ex yard |
— |
Reserved |
Every quantity above is measured off the rev 3 solid, not re-typed. If the client had
accepted a different revision, this list would be that revision's list. The glass run of
15 days is the longest external lead and is what places the barrier in week 4 of the
programme.
On acceptance 29 Aug
09:41
Quote accepted by K. Halvorsen. Rev 3 locked as the build revision.
09:41
Deposit invoice INV-0221 posted, $15,368.
09:41
Stock reserved on four SKUs; three purchase orders raised, PO-2211 to PO-2213.
09:42
Mould M-3 slotted for the week of 8 Sep.
09:42
Fabrication order FO-1184 released to the factory.
pending
Site start on deposit clearing; excavation week 1.