Q-1184 · Materials required
HALVORSEN · 14 Ferndale Ave, Chatswood NSW 2067
Accepted
Generated on acceptance · 29 Aug · from rev 3 geometry
Take-off against stock 8 SKUs · quantities off the solid
Material Required In stock To order Source Lead Status
Fibreglass shell, kidney 10.4TP-SHL-K1040 1 0 1 Own factory, mould M-3 2 wk Mould slotted
Spotted gum decking, 140 × 19TP-DEK-SPG 452 lm 280 lm 172 lm Timberline, Wetherill Park 5 d PO-2211
Bullnose coping, 500 mm unitsTP-COP-BN 61 64 — Ex yard — Reserved
Glass panel 12 mm, 1200 × 1200TP-BAR-GL12 33 12 21 Cut to order, Glasscorp 15 d PO-2212
Gate, hinges & latch setTP-BAR-GATE 1 3 — Ex yard — Reserved
Pump, filter & chlorinator setTP-PLT-SET 1 0 1 Waterco, distribution 4 d PO-2213
Hydraulic pipe & fittings, 50 mmTP-HYD-50 46 m 120 m — Ex yard — Reserved
Bedding sand & aggregateTP-CIV-BED 18 t 30 t — Ex yard — Reserved
Every quantity above is measured off the rev 3 solid, not re-typed. If the client had accepted a different revision, this list would be that revision's list. The glass run of 15 days is the longest external lead and is what places the barrier in week 4 of the programme.
On acceptance 29 Aug
09:41 Quote accepted by K. Halvorsen. Rev 3 locked as the build revision.
09:41 Deposit invoice INV-0221 posted, $15,368.
09:41 Stock reserved on four SKUs; three purchase orders raised, PO-2211 to PO-2213.
09:42 Mould M-3 slotted for the week of 8 Sep.
09:42 Fabrication order FO-1184 released to the factory.
pending Site start on deposit clearing; excavation week 1.
SKUs
8
from the take-off
Reserved
4
held against Q-1184
To order
4
3 POs + 1 mould slot
Committed
$31,940
POs raised on acceptance
Longest lead
15days
glass, cut to order
Handover
Week 5
held · factory has FO-1184
True Point · materials required Generated from the accepted revision; regenerates only if the document changes Q-1184 · rev 3 · 29 Aug